Photo Gallery

Home
About JH Choppers
Shop Tour
Apparel
Parts: Touring Dash Covers
Parts: Softail Dash Covers
Parts: Springer Adapters
Parts: Multi Fit Covers
Parts: One Offs
Parts: OEM
Bike Projects
Photo Gallery
Links
Blog
Contact

Whats New

Ignition Switch Covers

Check out these Touring Ignition Switch Covers. Chrome and Raw Finishes available. Black Anodized comming soon

AMD World Championship of Custom Bike Building

We had the great pleasure of being a Judge at the World Championship of Custom Bike Building

Whats Hot

Springer Riser Adapters

Check out these Springer Riser Adapters for after market springers from Paughco, MidUSAm MidWest and DNA

New Riding Shirts
New Riding Shirt
Check out this kick ass riding shirt Now Available


Quick Links:

Road King Candy Paint
Titan Sidewinder Fix
Road King Lowering Kit

Other Links:

Ring Roller Project

facebook
facebook

ebay deals
ebay deals


 

Welcome to the JH Choppers 1997 FXSTC Chopper Project Page.

Frame Modification: Its starting to look like a chopper now.

Frame Cut: Cut the backbone close to the seat mount. We are taking the stock "dip" out of the backbone and replacing it with a clean straight tube.

The upper tubes are then marked and cut. We leave a little extra tubing just before the curve. This will allow us to set the proper angle after the backbone length is finalized.
Backbone Cut
Downtube Cut
Frame Cut: After the stock neck is disconnected, all the old stock tubing from the cast iron neck is removed. This is were the new tubing will be installed/inserted.

The remaining frame connection points are then cleaned and prepared for welding.

Frame Cleanup
Neck Removed
Neck Cleanup
  
Backbone Fabrication: Based on the computer drawing, the new backbone tube was cut for a total backbone length of 27". The new 7 degree triple tree was assembled and attached to frame neck and the fuel tank set on the backbone.

The final backbone length was marked and cut Holes were drilled through the seat mount and the backbone for the spot welds to hold the inner tubing in place.
Tree Mock
Butt Joint
Butt Joint
Butt Joint
 
Setting the final Rake: The new 10" over fork tubes are attached to the triple tree with the front wheel installed. This is how the final rake will be determined. Before the final weld is applied, the front tire will be deflated to simulate the weight of the engine installed.

 

Final Rake
Down Tube Fabrication: With the front forks attached, the down tube length and angles can now be finalized. Small inner tubing is also cut, the upper connection inner tubing will have a small bend.
Down Tubes
Cutting Tubes
Upper Inner Tube
Lower Inner Tube
 
Frame Assembly/Alignment: The new downtubes and inners are installed. Small holes are drilled through the outside for spot welds to connect the inner tubing. The backbone alignment is set to the original position using a plum-bob. Spot and stitch welds are used to hold the alignment in place.
Alignment
Downtube Alignment
Downtube Alignment
   
Frame Assembly/Welding: With frame locked down and aligned, stitch and spot welds are added. During each weld, the plum-bob on the backbone is checked. After the backbone is located in, the plum-bob is moved to the neck and the more welds are applied. Additional checks are performed to insure the neck is true. After the frame is stitched welded together, the final plum-bob position is dead center.
Welding
Backbone Weld
Neck Welds
Dead Center
 

Completion of Frame Modification Phase: The frame modification phase is now completed. All the frame welds have been finalized. The end result is 4in stretch in the backbone, 7in in the downtubes and 40* degrees of rake at the neck.